We were going to pour the interior footings and elevator floor last week, but ran into weather and drawing conflicts (I thought I had all of them resolved… but found a couple of different items that need to be clarified…..). I am meeting with the Concrete, Framer, and the Plumbing Contractors on Monday to get everybody on the same page.
We will be installing the electrical and phone/data conduit on Tuesday. On Wednesday we will be pouring the interior footings and elevator floor. Then on Thursday form and pour the elevator walls. On Monday 3/29 we will pouring the slab.
We have had so many errors and hold ups….. Please Pray that we can accomplish these items that according to the schedule I have implemented (If they are according to God’s will) and for the rest of the building.
I will keep you updated each week as we progress through the building of our Lord’s house.
Sincerely,
Anton